Tozour successfully replaced 52 rooftop units for T.J. Maxx in just 3 hours! The project required a helicopter and thanks to meticulous advance planning, the Tozour team executed the job with precision. Once the units were safely secured on the building, the rooftop units were brought online and fully functional when business resumed after the holiday weekend. The project’s success has led to conversations for additional work.

Products/Services

52 Trane Voyager Rooftop Units; performed a turnkey replacement of existing units to Trane Voyager

Tracer SC-Plus controls upgrade; upgraded the existing Tracer Summit controls to the current Tracer SC-Plus controls